Asbestos refurbishment and demolition surveys
Identify materials that could be disturbed by planned refurbishment or demolition.
Match the survey to the work
The survey scope should reflect the areas and building elements affected by the planned refurbishment or demolition. Share current drawings, specifications, schedules and the proposed programme before the inspection.
Intrusive inspection and access
A refurbishment or demolition survey is intrusive and may involve opening up building elements. Survey areas should normally be unoccupied and appropriately isolated. The report records any inaccessible areas that need to be resolved before work starts.
Read HSE guidance on refurbishment surveys →Survey findings and report
The report sets out identified or presumed materials, sample results where taken, annotated plans, photographs, assessments, scope limitations and recommendations for the project team.
Use the findings in project planning
Review the report against the works package before tender and again before work begins. If the scope changes, check whether further survey information is required.
Pre-tender asbestos budget planning
Where the survey identifies asbestos likely to be affected by planned work, we can prepare an indicative budget using the findings, drawings, scope and proposed programme.
Discuss pre-tender asbestos budgeting →Common questions
Is a refurbishment survey destructive?
It is intrusive and may require destructive inspection to access concealed parts of the building fabric. The survey area must be planned and controlled.
Can the survey take place while the building is occupied?
The affected area should normally be vacated during intrusive inspection. If only part of a building is involved, suitable isolation and arrangements for safe reoccupation should be agreed.
What happens if an area cannot be accessed?
The limitation should be recorded. The area must not be disturbed until it has been inspected or otherwise managed using appropriate asbestos precautions.
Can the survey inform a pre-tender budget?
Yes. Findings can inform an indicative budget when considered alongside the drawings, scope, quantities, access and proposed programme. The budget is not a fixed quotation.